Short Summary
Partial Discharge (PD) testing during Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT) plays a crucial role in identifying insulation defects and ensuring the reliability of electrical equipment before commissioning. This buyer’s guide explains IEC 60270 measurement requirements, calibration and background noise considerations, equipment-specific acceptance criteria, and how to evaluate PD test reports. It also explores the role of conventional and non-conventional testing methods, the importance of comparing FAT and SAT results, and how to establish reliable baseline data for long-term condition monitoring. Learn what engineers and buyers should verify to ensure PD test results are accurate, meaningful and aligned with project requirements.
PD testing during FAT is your best chance to find hidden insulation defects before a transformer or switchgear panel leaves the factory. But a number in picocoulombs (pC) proves little on its own. What matters is how it was measured, what it was compared against and whether the equipment still behaves the same on site.
This guide is for engineers and buyers who specify or witness partial discharge testing at FAT and SAT. It covers what makes a test valid, how limits work, what to check in the report and why SAT still matters.
Why PD Is Measured at FAT
PD testing during FAT checks the insulation of electrical equipment under controlled high-voltage conditions before it is shipped. It identifies potential issues early, when they are still inexpensive and easy to resolve. It also creates the first record of how the insulation behaves.
Partial discharge (PD) refers to a localised electrical discharge that occurs within an insulation system without completely bridging the insulation between conductors. It can start in a gas void, a sharp edge, dirt, moisture or a poor joint. Each discharge is tiny, but over years they eat away at the insulation until it fails.
Failure in a transformer or switchboard means an outage, a safety risk and a long wait for a replacement. This is where Factory Acceptance Testing (FAT) earns its place. FAT is done at the manufacturer’s facility before delivery. Site Acceptance Testing (SAT) is carried out at the installation location to verify that the equipment remains in proper working condition and meets the required performance standards.
Factory PD testing gives the buyer three things:
- Early detection: defects are found where they can be fixed.
- Contract evidence: the result shows whether the equipment meets the agreed limits.
- A baseline: a reference for SAT and later monitoring.
A defect found at the factory may cost days of rework. Found after energisation, it can cost a failed unit. This highlights the importance of conducting PD testing during Factory Acceptance Testing (FAT).
IEC 60270 Measurement: What a Valid Test Needs
Accurate measurements in accordance with IEC 60270 require more than just a reliable testing instrument. The whole circuit must be set up well, calibrated as one system and checked for noise. Those three checks are the heart of how to perform PD testing during FAT properly.
IEC 60270 specifies the requirements for charge-based partial discharge (PD) measurements. The fourth edition, IEC 60270:2025, released on 5 June 2025, supersedes the previous 2000 edition and its 2015 amendment. Your contract may name an older edition, so confirm which one applies before testing begins.
A conventional IEC 60270 arrangement normally includes six parts:
- High-voltage test source: must itself be free of discharge.
- Equipment under test: the transformer, cable or switchgear.
- Coupling capacitor: gives PD pulses a path to the measuring circuit.
- Measuring impedance: turns pulses into a readable signal.
- PD measuring instrument: processes and displays the results.
- Calibration device: injects a known charge to scale the readings.
What Is Apparent Charge?
Under IEC 60270, partial discharge measurements are expressed in terms of apparent charge, measured in picocoulombs (pC). This is the charge that, injected at the test object’s terminals, would give the same reading. It is not the real charge inside the defect, so a pC value only means something when the test setup is clearly defined.
Why Full-Circuit Calibration Matters
PD measurement calibration must cover the complete circuit, with the equipment under test connected. A known charge is injected at the terminals and the scale is set from it. An instrument certificate alone is not enough, because leads, the coupling capacitor and the test object all change the signal.
How to Control Background Noise
Background noise is any interference that is not PD from the test object, such as supply noise, corona on leads or poor earthing. It must be measured, recorded and kept low enough to reveal PD at the specified level. Good grounding and shielding help.
A practical example: An engineer witnesses a factory PD test with a freshly calibrated instrument. The screen shows a low reading. But the full circuit was never calibrated with the transformer connected, and nobody recorded the noise. The reading looks good, yet it cannot be trusted. The instrument was calibrated. The measurement was not.
The same applies to PD testing equipment for FAT and SAT. Connecting a portable PD tester for transformer FAT and SAT does not make a test IEC 60270 compliant. The setup, calibration, conditions and procedure must all meet the standard.
How PD Testing During FAT Runs on a Transformer
For oil-immersed power transformers, PD is measured during the induced-voltage test. A typical sequence:
- Set up the circuit, earthing and shielding, then survey noise.
- Calibrate the complete measurement circuit with a known injected charge.
- Record the background noise and confirm it is low enough for the specified limit.
- Apply the specified voltage steps and hold periods.
- Record PD magnitude, repetition rate, pattern and trend.
- Assess the test results against the contractual requirements and the applicable edition of the standard.
Acceptance Criteria by Equipment Type
There is no single pass limit for partial discharge. Partial discharge acceptance criteria depend on the equipment, standard edition, test voltage, duration and contract.
Limits are set in three layers:
- IEC 60270 defines how charge-based PD is measured.
- Equipment standards, such as IEC 60076-3 for power transformers, set the test procedure and requirements.
- The purchase specification or contractual agreement defines the criteria against which the equipment’s acceptance is evaluated.
When you specify PD testing for factory acceptance testing, name all three. IEC 60270 on its own does not set an acceptable PD level.
| Equipment | Relevant standard or reference | What to check |
|---|---|---|
| Oil-immersed power transformers | IEC 60076-3:2013 + Amendment 1:2018 | PD measured during the induced-voltage test, at defined voltage levels and hold times. |
| Cast-resin dry-type transformers | IEC 60076-11 | Routine PD test after a pre-stress voltage, with the limit set in the edition your contract names. |
| Medium-voltage cables | IEC 60502-2 | Routine PD test where the standard and the cable specification require it. |
| Switchgear | IEC 62271 series, such as IEC 62271-200 for metal-enclosed switchgear, plus the project specification | Whether PD is measured, and the limit, depends on the switchgear type, voltage class, standard edition and purchase specification. |
What Do 100 pC and 250 pC Mean for Transformers?
These values come from the induced-voltage PD test in IEC 60076-3:2013, clause 11.3.5. They belong to one test sequence, not two separate pass marks.
- Background noise must not exceed 50 pC at the start and end, or the test is not valid.
- The voltage passes a check level of 1.2 Ur/√3, rises briefly to an enhancement level, then holds at 1.58 Ur/√3 for at least one hour. Ur is the rated voltage. PD is read about every five minutes.
- During that hour, PD must not exceed 250 pC or rise by more than 50 pC. There must be no rising trend in the last 20 minutes.
- Back at 1.2 Ur/√3 after the hour, PD must not exceed 100 pC.
A result outside these limits leads to investigation and discussion between purchaser and manufacturer, not automatic rejection. Older editions used different values, and contracts may set their own. Have a high-voltage test engineer confirm the clause in your contract’s edition.
What should a buyer verify before accepting a transformer PD result? The standard edition and contract limits, test voltage and duration, full-circuit calibration, background noise and how PD changed over the test. A low pC reading alone proves little.
Reading the Report as a Buyer
Judge a partial discharge test report on the quality of its evidence, not the “pass” on the last page. A good report lets an independent engineer see how each result was produced.
Buyer’s checklist for a PD test report:
- Was the applicable standard and edition identified?
- Was the complete measurement circuit calibrated?
- Is the calibration charge documented?
- Are background noise levels recorded?
- Are the test voltage and hold periods documented?
- Are PD magnitudes recorded in pC?
- Are pulse patterns and repetition rates available?
- Were abnormal readings or rising trends investigated?
- Does the report clearly state whether the equipment meets the agreed acceptance criteria?
Can a Low PD Reading Prove the Insulation Is Healthy?
No. A single low pC reading from PD testing during FAT does not prove healthy insulation. Noise may have hidden the PD, calibration may be incomplete, or the signal may fade before reaching the sensor. CIGRE warns that, for power transformers, apparent charge can differ widely with PD location, so it should not be the only focus. Repetition rate, trend and pattern add context.
What Does a PRPD Pattern Show?
A phase-resolved partial discharge (PRPD) pattern is a chart that plots each PD pulse against the point in the AC voltage cycle where it occurred. Voids, surface discharge and corona tend to form different shapes. PRPD patterns help engineers tell real PD from noise and give clues about the defect type. They are indications, not proof. Their reading should consider the test setup, noise sources and supporting measurements.
Before You Witness PD Testing During FAT: What to Ask For
Agree the report checklist above in the inspection and test plan. Then, on the day:
- Check the test circuit matches the agreed arrangement.
- Witness calibration with the transformer connected.
- See the background noise reading before voltage is applied.
- Watch live PD readings through each voltage step and hold.
- Raise any rising or unusual activity before the test ends.
- Leave with the signed report and calibration records.
What Changes at SAT
Partial discharge testing during SAT checks whether transport and installation have damaged the insulation. A clean result from PD testing during FAT shows the equipment left the factory in good condition, not that it arrived that way.
| Factor | FAT | SAT |
|---|---|---|
| Location | Manufacturer’s factory | Installation site |
| Main purpose | Verify manufacturing quality | Check for problems after transport and installation |
| Environment | More controlled | Potentially higher electrical noise |
| Main concern | Manufacturing or insulation defects | Transport damage, installation issues and site-related defects |
| Key benefit | Establishes factory baseline | Checks equipment condition before commissioning |
Conventional vs Non-Conventional PD Measurement
Sites are noisier, and a full conventional test circuit can be hard to set up. So SAT often combines conventional measurement, where practical, with non-conventional methods:
- UHF (Ultra-High Frequency): detects PD’s radio-frequency signals with sensors on the transformer tank.
- TEV (Transient Earth Voltage): detects PD inside metal-clad switchgear from outside.
- HFCT (High-Frequency Current Transformer): clamps around earth leads to detect PD in cables and joints.
- Acoustic and ultrasonic: pick up the sound of discharge, helping locate corona and PD inside a tank.
These methods are not interchangeable. Most are not calibrated in pC, so they suit detection and trending rather than a sole pass/fail decision.
Where Does UHF Fit?
UHF partial discharge measurement can support transformer FAT and SAT when a suitable sensor setup and calibration are in place. CIGRE Technical Brochure 861 (2022) proposes calibrating the measuring device and accessories (KM) and the sensor (KS), combined into one system factor (KUHF). Results are then expressed as field strength in volts per metre (V/m). For a buyer, the benefit is comparison. With the same sensors, positions and calibration, factory and site UHF readings can be compared more reliably. But V/m readings cannot be converted into IEC 60270 pC values, and CIGRE says UHF pass/fail thresholds are not yet feasible. UHF supports conventional testing. It does not automatically replace it.
Baseline Results for Later Condition Monitoring
Well-documented factory results are the reference for every later check. Without them, you cannot tell real ageing from a different setup.
To build a useful baseline:
- Record the first PD results, including magnitudes, patterns and repetition rates.
- Keep calibration records, coupling capacitance, frequency range and test layout.
- Compare FAT and SAT results using the same, clearly documented method.
- Monitor and investigate changes in discharge activity, online or offline, as the asset’s importance justifies.
Comparable conditions are essential. A rise in recorded PD does not automatically mean the insulation has worsened. A different sensor, calibration, test frequency, noise level or circuit can shift the result, which is why CIGRE recommends recording the setup in detail. Good records from PD testing during FAT let engineers compare like with like.
Frequently Asked Questions
Need Support With PD Testing During FAT or SAT?
A reliable partial discharge test is more than a reading in picocoulombs. It needs the right setup, full-circuit calibration, controlled noise and clearly agreed acceptance criteria.
Whether you are writing a transformer FAT specification, reviewing a manufacturer’s report or planning SAT, independent engineering support helps you check the evidence before commissioning. Sarom Global supports asset owners through owner’s engineering and FAT and SAT services. Contact us to discuss your requirements.