Remote Factory Acceptance Testing (Remote FAT) showing an industrial engineer virtually inspecting factory equipment through a laptop video call, with a safety helmet and industrial machinery.

Short Summary

A remote Factory Acceptance Test (FAT) allows buyers to witness equipment testing at a manufacturer’s facility through live video, screen sharing and digital test records, reducing the need for overseas travel. It works well for PLC logic, HMI demonstrations, alarm testing and documentation reviews, but has limitations when physical inspections, wiring checks or mechanical verification are required. This guide explains the differences between remote, hybrid and in-person FATs, the tests that can be conducted remotely, potential risks and cost savings, and how to choose the right approach for your project. Ultimately, the best FAT method depends on equipment complexity, inspection requirements and the consequences of missing a fault before shipment.

A remote factory acceptance test lets your engineers watch equipment being tested at an overseas factory without getting on a plane. Picture a UK engineering team that has bought a critical control system from a manufacturer in Asia. Before it ships, the system must pass its Factory Acceptance Test (FAT). In the past, two or three engineers would fly out to watch.

That trip means flights, hotels, time away from other work and calls across time zones. If travel is hard to book, the FAT date can slip and push back the ship date too.

A remote factory acceptance test, often called a virtual FAT, offers another way. Your team watches the tests on live video, reads the test papers online and talks straight to the factory’s test staff.

So when is a remote FAT enough? This guide compares remote, hybrid and in-person FAT so you can choose with confidence.

Quick Answer: When Should You Use a Remote FAT?

A remote factory acceptance test works when the system can be checked through live video, screen sharing, test records and results you can measure. It suits PLC logic, HMI demos, alarm tests and document reviews.

Hands-on checks of wiring, mechanical alignment, build quality or hidden parts may still need someone on site. If your project needs both software tests and key hands-on checks, a hybrid FAT is often the better balance.

What Is a Remote Factory Acceptance Test (FAT)?

A Factory Acceptance Test is a set of agreed checks done at the manufacturer’s plant before the system ships. It proves the system meets the specification while faults are still cheap to fix. The standard IEC 62381:2024 sets out rules and checklists for FAT on process control systems. It also helps the owner, buyer and vendor agree on scope and who does what. The standard does not, on its own, approve remote witnessing, and it leaves safety instrumented systems out of its scope. Whether remote testing suits your project still depends on the tests and what your project needs.

FAT is not the same as Site Acceptance Testing (SAT). FAT checks the system at the factory, often with test signals. SAT checks it once it is installed, wired to real field devices and running in real process conditions. A remote factory acceptance test never replaces SAT. It only changes how you witness the factory stage.

In a remote factory acceptance test, the buyer’s team joins online instead of flying out. Several cameras give wide and close-up views. Screen sharing shows the HMI (human-machine interface), PLC software and test data. Drawings, test steps, certificates and results are shared and signed off online.

For example, a UK firm buys a control panel from a maker in Germany. Instead of flying to Germany, the team joins a live session. They watch the tests, check the HMI screens and review the results from their own office.

The maker’s team still does all the hands-on work. Your remote team watches, asks questions, checks the proof and records the sign-off decision.

Remote FAT vs Hybrid FAT vs In-Person FAT: What Is the Difference?

There are three main ways to witness a FAT: a remote factory acceptance test, a hybrid FAT or an in-person visit.

 

Comparison factor Remote FAT Hybrid FAT In-person FAT
Customer attendance Online Online and physical Physical
Travel requirement Usually not required Required for selected activities Required
Live test witnessing Yes Yes Yes
Physical inspection Limited by available evidence and camera access Available for selected activities Direct physical access
Documentation review Digital Digital and physical Physical or digital
Travel expenses Generally lower Moderate, depending on attendance Generally higher
Best suited for Standardised, observable tests Mixed-risk equipment and test scopes Complex or hands-on inspections

Remote FAT: Remote factory acceptance testing suits tests that can be clearly shown through live video, test data and documents.

Hybrid FAT: A hybrid FAT pairs remote factory acceptance testing with an on-site witness for chosen key checks. Your main team stays home while one skilled person does the hands-on checks.

In-person FAT: This is still the best choice when direct access, close checks or hands-on use really matter.

The right choice depends on how complex the system is, what the tests need and what a missed fault would cost you.

Which FAT Tests Can Be Conducted Remotely, and Which Require an On-Site Witness?

A camera is very good at showing what a screen or gauge says. It is much less reliable at proving how something feels, fits or is built inside. Use the matrix below as a starting point when you plan a remote factory acceptance test.

Remote-Suitable vs Witness-Required Test Matrix

Test or inspection activity Remote suitability Recommended approach Why
HMI and SCADA screen demonstrations High Remote Screen sharing shows what the operator sees
PLC logic and sequence testing High, where test access and evidence are adequate Remote or hybrid Logic states show on screen
Alarm and interlock testing High, if signals and responses are visible and documented Remote or hybrid Inputs and responses show together
Functional performance testing Depends on equipment and test conditions Remote or hybrid Noise, heat and shaking may not show
Control panel visual inspection Partial Remote with detailed camera views; on-site if physical access is important Video flattens depth and hides corners
Wiring and termination inspection Partial Hybrid or on-site for critical connections A loose terminal can look perfect
Calibration certificate and document review High Remote Documents check well on screen
Physical workmanship inspection Limited On-site for critical or inaccessible areas Welds and fit need a close look
Mechanical alignment and internal component inspection Low for direct verification On-site Needs access and measuring
Safety-critical physical verification Risk-dependent On-site witness where physical verification is necessary Missed faults are costly
Final integrated system verification Depends on scope and test environment Often hybrid Many systems work together

Important: This is a general planning matrix, not a universal engineering standard. Agree the final test method against your spec, the standards that apply, project risks and acceptance criteria.

Tests That Generally Work Well in a Remote Factory Acceptance Test

These tests rely on data, screens and documents, which travel well over video:

  • HMI and operator screen demos
  • PLC sequence and logic tests
  • Alarm and interlock demos
  • Test report and calibration certificate review
  • Watching live readings, such as pressure or flow
  • Drawing and design document review

Tests That May Need Physical Attendance

These checks rely on touch, measuring or access that a camera cannot fully give:

  • Internal mechanical checks
  • Close build quality checks
  • Access and maintenance space checks
  • Checks where camera angles give too little proof
  • Hands-on tasks that video cannot properly show
  • Key checks where the test steps call for a direct look

The key point is simple. In a remote factory acceptance test, video can show what is happening. It cannot always prove what is happening inside a machine or behind a part you cannot see.

Illustrative Scenario: What a Camera Can Miss

This is an illustrative scenario based on common FAT findings. It is not a specific Sarom Global project.

The equipment: A US water utility ordered a PLC and motor control panel for a pump station from a builder in Southeast Asia.

Why remote seemed enough: Most of the scope was software: pump sequencing, alarms, interlocks and HMI screens. On paper, it suited a remote factory acceptance test.

What the on-site witness checked: The buyer added a local witness for half a day. That witness did random tug tests on field terminals and checked torque marks on power terminals.

What was found: Several I/O terminals pulled loose with light force. Some stranded wires had no ferrules.

Why video could not catch it: On camera, every wire sat neatly in place. Looseness is something you feel, not something you see. A video-only remote factory acceptance test would most likely have passed this panel.

Corrective action: The builder re-made the loose connections, torque-checked them with a calibrated tool and re-ran the affected I/O loop checks.

What could have happened: Shaking during shipping could have worked those wires looser. That can cause signals that come and go, false trips or hot terminals. These faults are slow and costly to find at start-up.

What Technology and Connectivity Do You Need for a Successful Virtual FAT?

A good remote FAT depends more on planning than on costly gear. Sort out these items before test day:

  1. Several camera angles: Wide, close-up, handheld and fixed views on the system. Schneider Electric has described using a 360-degree camera that can zoom in on small details.
  2. Live video calls: Two-way video and sound through a tool such as Microsoft Teams.
  3. Screen sharing: Access to the HMI, PLC screens, test software and live data.
  4. Stable internet: The speed you need depends on the number of feeds, picture quality and the tool you use, so test it first.
  5. Audio gear: Headsets and mics that work in a noisy factory.
  6. Shared documents: Drawings, the factory acceptance test procedure, calibration certificates, test reports and an action log.
  7. Recording: Record tests where allowed and agreed, with access and storage controls.
  8. Cyber security: Safe access, approved links, limited rights and protection of private data.
  9. Backup plans: A second connection or mobile hotspot, plus a phone line.

Valmet, for example, sends customers a short how-to video before each virtual FAT so they know how to prepare.

Video FAT Setup Checklist

  • Has the video setup been tested from end to end?
  • Can the camera operator move freely around the system?
  • Can people ask for close-up views?
  • Can everyone see the test steps?
  • Is the internet link reliable?
  • Is there a backup plan?
  • Have recording and file-sharing rights been agreed?

Who Should Witness and Approve a Remote Factory Acceptance Test?

Remote witness testing works best when everyone knows their job. A remote factory acceptance test often involves the supplier’s test team, the buyer’s chosen representative and, sometimes, an independent witness. Two roles matter most on the buyer’s side.

1. Local FAT Witness

A local witness stands in the maker’s plant on your behalf. Their tasks may include:

  • Checking equipment tags and serial numbers
  • Watching hands-on checks
  • Making sure the agreed tests are carried out
  • Asking for extra views or demos
  • Checking test records
  • Spotting faults you can see
  • Recording deviations and open issues

2. Remote Engineering Reviewer

The remote reviewer joins by video and works from shared documents. Their tasks may include:

  • Reviewing the design specs
  • Watching the tests
  • Checking test results
  • Asking questions and asking for demos
  • Reviewing deviations
  • Giving expert advice

The supplier’s team runs the tests. The buyer’s representative judges the results. An independent witness gives a fair account of what happened on the factory floor.

Who has final sign-off? In a remote factory acceptance test, neither the remote reviewer nor the local witness has the right to approve shipping by default. Your contract and sign-off process should name who does.

What Experienced FAT Witnesses Look For Beyond the Test Results

A passed test is only part of the picture. A good witness also checks:

  • That the unit on test matches the approved specification and is the actual unit ordered
  • That test conditions match the agreed acceptance criteria
  • That deviations are written down, not brushed aside
  • That build quality supports long, reliable service
  • That open issues are closed out before shipping

Need an independent FAT witness at your supplier’s factory? Not every check can be done remotely. Sarom Global gives on-site engineering and FAT witnessing support across Europe, Asia and the Americas. We help buyers check equipment, inspect build quality and record deviations before shipping. 

What Are the Risks of a Remote Factory Acceptance Test, and How Can You Manage Them?

Virtual FATs have limits, mainly where hands-on checks are needed. A guest column on Pharmaceutical Online warned that remote FATs raise the chance of a system shipping without meeting user needs. Most of these risks can be managed.

Risk How to manage it
Limited physical visibility Arrange multiple cameras and an on-site witness for critical inspections
Poor connectivity Test connections beforehand and set up backup communication
Incomplete test documentation Agree the FAT protocol, records and acceptance criteria before testing
Delayed issue resolution Assign technical decision-makers and keep a live action log
Unclear acceptance responsibilities Define sign-off authority and deviation procedures in the contract

Recorded Video Is Not the Same as Live Witnessing

A recording is useful back-up proof, but it is not the same as watching live. Watching live, you can ask questions, ask for a new camera angle and look into a strange result. With a recording, you only see what the camera operator chose to show.

Remote FAT Pre-Approval Checklist

Remote FAT best practices start before the purchase order is signed. Before you agree to remote witnessing, make sure that:

  • The buyer and supplier have agreed the exact test scope
  • Every test has clear pass/fail criteria you can measure
  • The documents you need are listed
  • Tests that need someone on site are flagged and given to a skilled witness
  • Equipment serial numbers and tags will be checked
  • Recording and proof needs are agreed
  • The way to record and fix deviations is written down
  • The person who can give conditional sign-off is named
  • The person with the final say on shipping is named
  • A fallback is agreed if the link drops or a test cannot be finished

Remote FAT vs In-Person FAT: How Much Can You Save on Travel Costs?

Travel savings are real, but not a given. They depend on your project.

FAT travel cost items for an in-person visit:

  • Overseas flights
  • Hotels
  • Local transport
  • Meals and daily allowances
  • Travel time
  • Engineer hours lost to travel
  • Possible project delays

Costs that come with remote FAT:

  • Remote camera and sound gear
  • Video call and tech setup
  • Local witness fees, if needed
  • Engineer time
  • Managing documents and recordings

Use this simple formula:

Potential net saving = Avoided travel and related costs − Extra remote FAT costs

Your result depends on how many engineers would travel, where the factory is, how long the FAT runs and whether you need a local witness.

Illustrative example: two engineers, a five-day FAT, compared with a hybrid FAT using one local witness for two days.

Cost item In-person FAT Hybrid FAT
Travel for two engineers (flights, hotel, allowances) US$12,000 US$0
Local witness (two days) US$0 US$3,000
Remote setup (cameras, headsets, connection) US$0 US$500
Total direct cost US$12,000 US$3,500
Potential net saving US$8,500

Assumed figures as an example only, not Sarom Global quotes. Engineer pay and project delays are left out. The in-person option would also cost about four engineer days in travel time.

A hybrid FAT often costs more than a fully remote one. For high-risk systems, that extra cost buys the hands-on checks that matter most.

How to Decide Whether You Need a Remote, Hybrid or In-Person FAT

Use these three lists to decide whether a remote factory acceptance test, a hybrid FAT or an in-person visit fits your project.

Choose a Remote Factory Acceptance Test When:

  • The design is final
  • The test scope is clearly written down
  • Most acceptance criteria can be measured
  • The supplier can give live camera access
  • Test results can be checked online
  • Hands-on checks are not needed for the agreed scope

Choose Hybrid FAT When:

  • Most tests can be done remotely
  • Some checks need hands-on access
  • The system has complex mechanical or electrical links
  • You want an independent check on site
  • Some tests carry a higher cost if they fail

Choose In-Person FAT When:

  • The system is highly complex or a new design
  • Direct hands-on checks are a must
  • Key tests cannot be properly seen remotely
  • Safety or approval rules call for hands-on checks
  • A missed fault would have serious results

Hybrid FAT is often a sensible middle ground, but it is not the default answer for every project. Match the method to the risk.

How Sarom Global Can Support Your Factory Acceptance Testing

Sarom Global is a global industrial engineering consulting and technical services firm based in Australia. We support projects across Asia-Pacific, EMEA and the Americas. Our focus is process control, plant automation and instruments for oil and gas, power, utilities and process plants.

Whether you choose a remote factory acceptance test, a hybrid FAT or a full site visit, we can help with:

  • On-site engineering and tech support
  • Equipment and control system testing, including DCS and PLC systems
  • Tech checks and inspections
  • Contractor and OEM coordination
  • Independent owner’s engineering support
  • Remote and specialist consulting

Some checks simply cannot be done through a camera. At those times, a skilled engineer on the factory floor protects your spec, budget and schedule, working as part of your own team.

Sarom can act as your on-site FAT witness in Europe, Asia and the Americas. Our engineering team can support equipment inspections, testing, technical verification and coordination with manufacturers, helping you protect project requirements before equipment is shipped.

Frequently Asked Questions About Remote Factory Acceptance Testing

Is a remote factory acceptance test as reliable as an in-person FAT?
For the right tests, yes. A remote factory acceptance test gives reliable proof when the scope, test steps, camera views, live talk and documents are well controlled. It cannot replace hands-on checks where direct access is needed, such as internal mechanical checks or loose wiring.

What equipment do you need for a virtual FAT?
A virtual FAT often needs several cameras, stable internet, two-way video calls, mics and headsets, screen sharing and access to shared test documents. For PLC and DCS tests, remote team members should also see the software screens and test results live.

Can a remote factory acceptance test be used for SIL-rated systems?
Joining some FAT tasks remotely for a safety instrumented system (SIS) may be possible. But it cannot replace the checks, tests and records that the functional safety life cycle needs. IEC 62381:2024 leaves SIS out of its scope, so the project must follow IEC 61511 and its approved safety steps. A remote factory acceptance test does not, by itself, meet SIL verification or validation needs.

Who signs off a remote factory acceptance test?
The buyer’s chosen representative or named project lead often approves the FAT result, based on the contract and sign-off process. The supplier and any independent witness give back-up proof but do not have the final say by default.

How much does a remote factory acceptance test save?
It depends on your project. Savings come from avoided travel, team size, where the factory is and how long the test runs, minus extra remote setup or local witness costs. Compare the total cost of a remote factory acceptance test, a hybrid FAT and an in-person visit for your project.

Is a hybrid FAT better than a remote FAT?
A hybrid FAT is better when most tests can be watched remotely but some key checks need hands-on access. It joins live remote viewing with an on-site engineer who can check wiring, mechanical parts and build quality that cameras cannot fully show. A fully remote FAT may be enough for standard tests where every acceptance criterion can be shown on screen.